Installation of a water storage system for the water treatment plant (WTP), with a total capacity of 800 m³, and construction of the foundation for a compact wastewater treatment plant (WWTP).
Execution of a project aimed at expanding the storage capacity of the Treated Water Supply and Distribution System in the municipality of São Francisco do Sul, Santa Catarina, involving the installation of two interconnected metal reservoirs, each with a capacity of 400 m³, for a total storage capacity of 800 m³.
The services include:
- preparation of detailed design drawings for the storage and pressure-boosting system;
- construction of foundations, structural bases, and support structures;
- fabrication, transportation, and assembly of the two metal reservoirs;
- installation of hydraulic systems and interconnections;
- installation of suction and pressure lines, including valves, fittings, and accessories;
- installation and assembly of the pumping system;
- installation of electrical systems, including control panels and operational devices;
- earthwork, site grading, and drainage services;
- performance of hydrostatic, electrical, hydraulic, and operational tests;
- commissioning of the system, ensuring proper functioning and operational readiness.